NOCs FOR STRUCTURES
<span>Print</span>
S. No. | Name of Structure | Location | Applicant Name | Reference | Applicant Date | Noc Issued Date | Approved Clearance in (m) | |
---|---|---|---|---|---|---|---|---|
Horizontal | Vertical | |||||||
1 | Construction of Road Bridge of NHAI at Nakhwa (Varanasi) | at Ch: 1302 Km near Nakhwa across river Ganga in Ghazipur-Varanasi stretch of NW-1 (Under Class-VI) | General Manager cum Project Director, NHAI PIU, Varanansi | No. IWAI/PTN/17(20)/NC(2)/2015-16/1078 | 06/30/2015 | 10/01/2015 | > (Greater Than)82 | > (Greater Than)10.11 |
2 | Construction of 6 lane Cable Stayed Road Bridge at Bansberia, Kalyani (WB). | at Ch: 191.30 Km D/s of existing Iswar Gupta Setu in Haldia-Farakka stretch of NW-1, Bansberia, Kalyani (Under Class-VII). | Chief General Manager, West Bengal Highway Development Corporation (WBHDC) through RITES Ltd. | No.IWAI/KOL/SUR(03)/Permission/2015-16/008 | 05/29/2015 | 09/21/2015 | 108 | 10 |
3 | Construction of tower foundation of 400 KV D/C Rajarhat-Purnea overhead transmission line under ERSS-V by Power Grid Corporation of India, Kolkata. | Across river Bhagirathi between Rasulpur Char and Sunderpur Char near Behula Rly station under Nadia and Hooghly (W.B.) at Ch. 226 km in Tribeni-Swaroopganj stretch of NW-1 (Under Class VII) | DGM (TL Construction), Power Grid Corporation of India Ltd., ER-II, Kolkata. | No. IWAI/KOL/SUR(14A)/ 2014-15/1123 | 06/16/2014 | 09/15/2014 | 520 | 31.14 |
4 | Construction of tower foundation of 400 KV D/C Rajarhat-Purnea overhead transmission line under ERSS-V by Power Grid Corporation of India, Kolkata. | Across river Ganga between Bakeya Deara and Bakeya Rani Chak D/s Karagola Ghat in Dist. Katihar, Bihar at Ch. 651 km in Rajmahal-Bhagalpur stretch of NW-1 (Under Class VII) | DGM (TL Construction), Power Grid Corporation of India Ltd., ER-II, Kolkata. | No. IWAI/PTN/17(20)/NC/ 2014-15/1600 | 06/16/2014 | 12/27/2014 | 530 | 23.35 |
5 | Construction of Water Delivery System (Intake well) RCC/ Steel Structure on Ganga for Barauni Thermal Power Station by BSPGCL, Patna. | At U/s Semaria ghat, near Rajendra Bridge (Ch: 897 Km), Dist. Begusarai (Bihar) in Munger - Patna stretch of NW-1 (Under Class VII) | Chief Engineer (P&D) Bihar State Power Generation Company Limited, Vidyut Bhwan Bailey Road, Patna. | No. IWAI/PTN/17(20)/NC/ 2013-14/2482 | 02/20/2014 | 03/27/2014 | 43.5 | 0 |
6 | Const. of five (5) Road Bridges across Ganga between Ghazipur and Mirzapur in the state of U.P. by UPSBCL/ UP PWD | At Zamania, Saidpur, Balua, Chunar & Bhatauli in Ghazipur- Allahabad stretch of NW-1(Under Class VI) | 1. Joint Managing Director, UPSBCL Varunapul, Varanasi. 2. Chief Engineer (Bridge), UP PWD, Nirman Bhawan, Lucknow (UP) | No. IWAI/PR/NW-1/Nav. clearance/2013-14 | 01/18/2014 | 02/19/2014 | > (Greater Than)80 | > (Greater Than)10 |
7 | Const. of tower foundation for 400 KV D/C Barh-Gorakhpur Overhead Transmission line. | At Village Matiyour -Achaura (Ch: 897 Km) in Munger - Patna stretch of NW-1 (Under Class VII) | Deputy General Manager, Power Grid Corporation of India Ltd., ERTS-1, NH-77, P.O. Dariyapur, Turki Muzaffarpur (Bihar) | No. IWAI/PTN/17(20)/NC/ 2013-14/2067 | 10/25/2013 | 01/29/2014 | 522 | 24.36 |
8 | Permission for const. of Intake Jetty for implement of surface water supply scheme for Bally - Jagacha Block, in Dist. Howrah (W.B.) | At KoPT area, near Bally bridge on river Hooghly in Haldia - Patna stretch of NW-1 (Under Class VII) | Chief Engineer, Directorate of Public Health Engineering, Kolkata, Govt. of West Bengal | No. IWAI/KOL/SUR(14A)/ 2013-14/1054 | 09/10/2013 | 10/08/2013 | 40 | 0 |
9 | Const. of Road Bridge across NW-1 at Samneyghat, Dist. Varanasi (U.P.) by UPSBCL/ UPPWD | At Samneyghat (Ch: 1316 Km), Dist. Varanasi (U.P.) in Patna – Allahabad stretch of NW-1 (Under Class VI) | Project Manager, Bridge Construction Unit-I, U.P. State Bridge Corporation Ltd., Old Normal School, Shivpur, Varanasi (U.P.) | No. IWAI/PR/NW-1/Nav. clearance/2013-14 | 08/16/2013 | 10/08/2013 | > (Greater Than)80 | > (Greater Than)10 |
10 | Construction of 110 MGD Jetty & Raw water pumping station (intake point) at Garden Reach Area, Kolkata(WB) | At Garden Reach Area on river Hooghly (Kolkata) in Haldia-Patna stretch of NW-1 (Under Class VII) | Director General, Water Supply Department, Kolkata Municipal Corporation, Kolkata (W.B.) | No. IWAI/KOL/SUR(14A)/ 2013-14/846 | 06/19/2013 | 09/02/2013 | 35 | 0 |
11 | Construction of gangway jetty (intake point) at Gopalpur, Chaknai Ghat Dist. Vaishali (Bihar) | At Gopalpur (Ch: 938 Km) near Chechar, about 17 Km D/S of Patna in Haldia-Patna stretch of NW-1 (Under Class VII) | Chief Engineer (Urban) Public Health Engineering (PHED) Department, Govt. of Bihar (Patna) | No. IWAI/PTN/17(20)/NC/ 2013-14/875 | 05/10/2013 | 07/31/2013 | 65 | 0 |
12 | Const. of road bridge across river Ganga (NW-I) for four laning of Khagaria-Bakhtiyarpur section of NH-31in the State of Bihar. | At Semaria - Hatidah (Ch. 851) near Mokama in Haldia - Patna stretch of NW-1 (Under Class VII) | Project Director (T), PD PIU, NHAI, Harpur, PO Tilrath, Dist. Begusarai (Bihar) | No. IWAI/PTN/17(20)/NC/ 2013-14/876 | 05/04/2013 | 08/07/2013 | 108 | 10 |
13 | Const. of tower foundation for 400 KV D/C Sasaram-Varanasi O/head Transmission line. | At Village Pakri/Mwah (Ch: 1341 Km) D/s Chunar in Patna-Allahabad stretch of NW-1 (Under Class VI) | Chief Manager (TL Construction), Power Grid Corporation of India Ltd., Sunderpur, Varanasi (U.P.) | No. IWAI/PTN/17(20)/NC/ 2013-14/1396 | 04/15/2013 | 10/21/2013 | 610 | 22.3 |
14 | Const. of tower foundation for 765 KV S/C Gaya - Varanasi overhead Transmission line | At Basaratpur/ Mohna (Ch: 1342 Km) near Chunar, Mirzapur (U.P) in Patna - Allahabad stretch of NW-1 (Under Class VI) | Deputy General Manager, Power Grid Corporation of India Ltd., Jagatganj, Varanasi (U.P.) | No. IWAI/PTN/17(20)/NC/ 2013-14/1397 | 02/12/2013 | 10/21/2013 | 450 | 28.4 |
15 | Construction of foundation of tower for 220 KV S/C Aurai-Mirzapur transmission line near Mirzapur (U.P.) | At Ch: 1380.5 Km of NW-1 near Mirzapur, U.P. in Patna-Allahabad stretch of NW-1 (Under Class VI) | Executive Engineer, Electricity Div. IV, UP Power Transmission. Corporation, DLW, Varanasi (U.P.) | No. IWAI/PR/ NW-1 / Navigation Clearance/2012-13 | 09/27/2012 | 01/15/2013 | 900 | 23 |
16 | Construction of major railway bridge across river Bhagirathi at 1.70 Km on State Highway No.8, Nabadwip, Dist. Krishnanagar (W.B.) | At Ch: 278.30 Km of NW-1 D/s Gauranga Setu Nabadwip (W.B) (Under Class VII) | Chief Project Manager, Rail Vikas Nigam Ltd., Rash Bihari, Avenue Kolkata (W.B.) | No. IWAI/PR/ NW-1 / Navigation Clearance/2012-13 | 08/14/2012 | 12/20/2012 | 101 | 10.2 |
17 | Construction of structure (intake well) for drawls of water from River Ganga at Barh, Dist. Patna (Bihar) | At NTPC Barh, Dist. Patna in Haldia-Patna stretch of NW-1 (Under Class VII) | General Manger, NTPC Ltd., Barh, Dist. Patna (Bihar) | No. IWAI/PR/ NW-1 / Navigation Clearance/2012-13 | 08/14/2012 | 09/13/2012 | 0 | 0 |
18 | Construction of bridge across Hatania- Doania at Ch: 112.35 of NH-117, Dist. 24-Pargana (W.B.) | At Hatania- Doania River in Indo-Bangladesh Protocol route (Under Class VII) | Superintending Engineer, N.H. Design and Planning Circle, PW (Roads) Directorate, Kolkata | No. IWAI/PR/ NW-1 / Navigation Clearance/2012-13 | 08/01/2012 | 09/03/2012 | 108 | 10.37 |
19 | Construction of Ganga Path (Driveway) in Patna region by BSRDCL. | From Digha ghat to Didarganj via. Gaighat in Dist. Patna (Bihar) | General Manager, Bihar State Road Dev. Corporation Ltd, Sheikhpura, Patna (Bihar) | No. IWAI/PR/1/Nav. clearance/2013-14-II | 07/10/2012 | 09/30/2013 | 0 | 0 |
20 | Construction of two lane bridge over feeder canal at Km 259-950 of NH-34 Farakka (W.B.) | At near Ahiron (Ch:509.4Km) 20m D/s of existing bridge over feeder canal, Farakka Dist. Murshidabad (W.B.) | Project Director, Implementation Malda Unit, P.O. Mangalbari (W.B.) | No. IWAI/PR/ NW-1 / Navigation Clearance/2012-13 | 05/09/2012 | 01/11/2013 | 74.9 | 10.12 |
21 | Construction of four lane bridge across River Bhagirathi at 195 + 160 of NH-34 near Berhampur (W.B.) | At Ch: 418 near Berhampur (W.B.) in Haldia-Patna stretch of NW-1 (Under Class VII) | Project Director, NHAI, Malda Unit, Mangalbari (W.B.) | No. IWAI/PR/ NW-1 / Navigation Clearance/2012-13 | 05/09/2012 | 07/20/2012 | 100 | > (Greater Than)10 |
22 | Construction of foundation for 400 KV D/C Kishanganj, Patna transmission line Munger (Bihar) | At Mahenderpur-Surajgarha near Munger (Bihar) in Haldia – Patna stretch of NW-1 (Under Class VII) | Deputy General (TLC), Power Grid Corporation of India Ltd., Boring Road (Patna) | No. IWAI/PR/ NW-1 / Navigation Clearance/2012-13 | 03/15/2012 | 08/13/2012 | 540 | 23.5 |
23 | Construction of Road Bridge across river Ganga between Arrah & Chhapra connecting NH-30 and NH-19 (Bihar) | At Babura -Doriganj, Near Arrah, Bhojpur (Bihar) in Patna -Allahabad stretch of NW-1 (Under Class VI) | M/s S.P. Sighla Constructions Pvt. Ltd., Boring Road, Patna (Bihar) | No. IWAI/PR/1/Navigation Clearance/2011 | 02/08/2012 | 06/05/2012 | 117.6 | > (Greater Than)10 |
24 | Construction of new two-lane road bridge adjacent to the existing bridge over feeder canal, Farakka, Murshidabad (W.B.) | At RD 8.5 in Feeder canal, Farakka, W.B. in Haldia–Patna stretch of NW-1 (Under Class VII) | Deputy General Manager (FAQ), NTPC Limited, Farakka Super Thermal Power Station, Dist. Murshidabad (W.B.) | No. IWAI/PR/1/Navigation Clearance/2011 | 11/24/2011 | 01/05/2011 | 73.3 | > (Greater Than)10 |
25 | Construction of foundation/ installation of tower for 400 KV D/C (Quad) Purnia-Bihar Sharif transmission line (Bihar) | At SAMHO & Mahenderpur between Munger and Semaria in Haldia –Patna stretch of NW-1 (Under Class VII) | Deputy General Manager, East-North Interconnection Company Ltd., Ward No. 14, Gurudwara Road, Purnia (Bihar) | No. IWAI/PR/1/Navigation Clearance/2011 | 08/09/2011 | 09/23/2011 | 570 | 22.5 |
26 | Construction of structure of Dakara Nala Pump, Canal station in Dist. Munger (Bihar) | At Surajgarha, Dist. Munger (Bihar) in Haldia-Patna stretch of NW-1 (Under Class VII) | Executive Engineer, Ganga Pump Canal Division, Surajgarha Camp, Munger (Bihar) | No. IWAI/PR/1/Navigation Clearance/2011-12 | 07/01/2011 | 08/19/2011 | 0 | 0 |
27 | Construction of tower for 765 KV S/C Sasaram - Fatehpur, transmission line in Varanasi (U.P.) | At Shivpur, Dist. Varanasi (U.P) in Patna-Allahabad stretch of NW-1 (Under Class VI) | Chief Manager, Power Grid Corporation of India Limited, Sunderpur, Varanasi (U.P.) | No. IWAI/PR/1/Navigation Clearance/2011 | 06/06/2011 | 06/20/2011 | 580 | 25.55 |
28 | Construction of Road bridge connecting Bakhtiyarpur bypass of NH-31 and NH-28 at Tajpur (Bihar) | At Rupas near Barh, Dist. Patna in Haldia-Patna stretch of NW-1 (Under Class VII) | Chief Manager Project, Navayug Engineering Company Ltd., Patliputra colony, Patna (Bihar) | No. IWAI/PR/1/Navigation Clearance/2011 | 04/02/2011 | 05/19/2011 | 125 | 10.67 |
29 | Construction of Road Bridge at Baluaghat, Dist. Varanasi (U.P.) | At Baluaghat (Ch:1281.50Km), Dist. Varanasi, (U.P) in Patna- Allahabad stretch of NW-1 (Under Class VI) | Deputy Project Manager, U.P. State Bridge Corporation Ltd., Shivpuri, Varanasi (U.P.) | No. IWAI/PR/1/Navigation Clearance/2010 | 11/30/2010 | 01/05/2011 | > (Greater Than)80 | 10 |
30 | Construction of Rail bridge between Namkhana and Chandra Nagar in Sealdah Div. of Eastern Railway | At Hatania-Doamia river in the Sunderban (W.B.) (Under Class VII) | Deputy Chief Engineer/Construction/JB/ER, Eastern Railway office, Kolkata (W.B.) | No. IWAI/PR/1/Navigation Clearance/2010 | 10/11/2010 | 11/19/2010 | 100 | 10 |
31 | Construction and installation of tower for 765 KV S/C (Quad) Anpara - Jhusi Transmission line | At Laksagrih (Ch: 1495.8 Km) near Sirsa, Dist. Allahabad (U.P.) in Patna-Allahabad stretch of NW-1 (Under Class VI) | Executive Engineer, U.P. Power Transmission Corporation Ltd, Mirzapur (U.P.) | No. IWAI/PR/1/Navigation Clearance/2010 | 09/20/2010 | 12/14/2010 | 408 | 27.6 |
32 | Construction of tower (Pile Foundation) for 765KV S/C Sasaram Fatehpur Transmission line. | At Shivpur(Ch:1330 km)Varanasi(U.P.) in Patna- Allahabad stretch of NW-1(Under Class-VI) | Chief Manager,Power Corporation of India Ltd., Sunderpur, near Life Line Hospital,Varanasi (U.P.) | No.IWAI/PR/1/Navigation Clearance/2010 | 06/04/2010 | 07/19/2010 | 580 | 26.8 |
33 | Construction/Installation of 220 KV RC Tower,Sahupuri,Bhelupur,D.C. transmission line. | At Samane Ghat,Dist. Varanasi,(U.P.) in Patna-Allahabad stretch of NW-1 (Under Class-VI) | Executive Engineer,Electricity Transmission Div.III,U.P. Power Transmission Corporation Ltd., Sahupuri,Varanasi(U.P.) | No.IWAI/PR/1/Navigation Clearance/2008 | 05/11/2009 | 07/10/2009 | > (Greater Than)80 | 20.1 |
34 | Construction/Installation ofTower for 765 KV Gaya-Ballia Transmission lines. | At Chausa near (kamaria village),dist.Buxer,Bihar in Patn-Allahabad stretch of NW-1(Under ClassVI) | Chief Manager,Power Grid Corporation of India Limited,Buxar(Bihar) | No.IWAI/PR/1/Navigation Clearance/2008 | 04/24/2009 | 07/10/2009 | > (Greater Than)80 | 25.55 |
35 | Construction ofTower Foundation(Pile) &Superstructure of Power line (400 KV Barh-Ballia transmission lines) | At Nanijore(Ch:1063Km) Near Prabothpur ghat Dist.Ballia(U.P.) in Patna-Allahabad stretch of NW-1(Under Class-VI) | Chief Manager,Powergrid Corporation of India Limited, Buxar (Bihar) | No.IWAI/PR/1/Navigation Clearance/2008 | 03/31/2008 | 06/17/2008 | > (Greater Than)80 | 21.9 |
36 | Construction of tower foundation for installation of 132 KV S/C Pholpur-Teliarganj transmission line. | At Teliarganj near Sangam, Allahabad, UP in Patna-Allahabad stretch of NW-1(Under Class VI) | Executive Engineer,Electricity Transmission Div.-II,VP Tower Transmission Corporation Ltd.., Allahabad(U.P.) | No.IWAI/PR/1/Navigation Clearance/2008 | 02/14/2008 | 04/05/2008 | > (Greater Than)80 | 19.22 |
S. No. | Name of Structure | Location | Applicant Name | Reference | Applicant Date | Noc Issued Date | Approved Clearance in (m) | |
---|---|---|---|---|---|---|---|---|
Horizontal | Vertical | |||||||
1 | Construction of Intake well for South East Guwahati Water Supply Project. | At Ch: 265 Km near IOCL Gate, Sector-1, Guwahati | Design and Supervision Consultancy for Assam Urban Infrastructure Investment Program (AUIIP) | No. IWAI/GHY/3(20)/NC/2007-08/449 | 07/23/2015 | 09/22/2015 | 50 | 0 |
2 | Laying of transmission line upstream of Naranarayan Setu, Jogighopa | U/s of Jogighopa Bridge, (NW2, Class-VII ); Ch. 108km | M/s NETC Ltd(North East Transmission Co. Ltd.) | IWAI/PR/2/Nav.cl/2007 | 05/25/2009 | 01/15/2010 | > (Greater Than)1000 | > (Greater Than)22 |
3 | Construction of passenger ropeway between Guwahati and North Guwahati | U/s of Umananda, Guwahati (NW2, Class-VII ); Ch:260 km | M/s Damodar Ropeways &Construction Co. (P)Ltd | IWAI/PR/2/Nav.cl/2007 | 01/30/2009 | 05/13/2009 | > (Greater Than)480 | > (Greater Than)12 |
S. No. | Name of Structure | Location | Applicant Name | Reference | Applicant Date | Noc Issued Date | Approved Clearance in (m) | |
---|---|---|---|---|---|---|---|---|
Horizontal | Vertical | |||||||
1 | Construction of Thottappally - Naluchira Bridge across Pamba River in Alappuzha | chainage- 124 km | Executive Engineer, PWD Road Division, Collectorate Building Alappuzha -688001 | IWAI/NOC/KM&ML/NW3/2018 | 01/30/2019 | 04/12/2019 | 40 | 6 |
2 | Construction of foot Over bridge across NW-3(TS Canal) for MS unit of KMML at Chavara | Chainage- 166.0 km | The Assistant General Manager (Projects) Mineral Sepration Unit Kovilthottam Chavara Kollam- 691583 | IWAI/NC/KM&ML/NW-3/2018 | 11/20/2018 | 02/13/2019 | 40.273 | 6.2 |
3 | Laying of power cable across TS canal through Horizontal Directional Drilling Method | Chainage- 166.0 km | Laying of power cable across TS canal through Horizontal Directional Drilling Method | IWAI/NC/KM&ML/TS Canal/2018 | 08/31/2018 | 11/26/2018 | - | - |
4 | Footover bridge at Nehru Trophy starting point, Alappuzha | Chainage- 95.5 km | Secretary, Alappuzha Municipality | IWAI/NC/Nehru Trophy/2018 | 05/24/2018 | 07/23/2018 | 59.8 | 7 |
5 | Upgradation of transmission line | Chainage-63.0 km | Dy. Chief Engineer, Transgrid South, HMT colony, Kalamsaaerry | IWAI/NC/KSEBL/NW-3/2018 | 01/20/2018 | 05/16/2018 | 230M From West Pylon & 270m from east pylon | 19.6 m to 22.6 m |
6 | Construction of structure for extension of Asramom link road-phase III-IV-Extension upto Thoppil Kadavu in kollam | Chainage- 180.0 km | Executive Engineer, PWD Road Division, Kollam-691001 | IWAI/PLNW-3/18/93(143) | 05/26/2017 | 05/26/2017 | 47 | 7 |
7 | Construction of Bridge at Nedumudy- Karuvatta road, Alappuzha | Chainage- 122.60 km | The Executive Engineer, PWD Road Division, Alappuzha | IWAI/NC/NW-3/2017 | 05/24/2017 | 08/02/2017 | 49.46 | 7 |
8 | Construction of bridge at Mackeykadavu - Nerekadavu road, Alappuzha | Chainage-63.0 km | The Executive Engineer, PWD Road Division | IWAI/NC/NW-3/2017 | 05/24/2017 | 08/09/2021 | 42.8 | 7 |
9 | Chambakkara Bridge across Chamakkara Canal in NW-3 | Chambakkara Canal | Chief Engineer, Delhi Metro Rail Corporation Ltd., Kochi rail Project, Eastern Entry Tower, Kochi-682016 | IWAI/PLNW-3/18/93(145) | 11/16/2016 | 05/26/2017 | 40 | 7 |
10 | Rail bridge across National Waterway No. 3 (Arror Kayal) under Kumbalam-Thuravur track doubling work | chainage 45.60 km | Chief Engineer construction, Ernakulam, Southern Railway | W. 71/I/CN/ERS/EAK 31 dated 01.12.2015 | 12/01/2015 | 01/14/2015 | 43.93 | 7.47 |
11 | Rail bridge across National Waterway No. 3 (River Pamba) under Haripad - Ambalapuzha track doubling work | Chainage 122.30 Km | Chief Administrative Officer (CAO), Construction, Southern Railway, Ernakulam | letter no. W.182/I/CN/ERS/AMPA-HAD dated 28.07.15 & 28.10.2015. | 10/28/2015 | 11/16/2015 | 40 | 7 |
12 | Construction of two lane bridge with paved shoulders, Kollam Bypass of NH 47 (New NH 66) from Kavanadu | chainage 177.20 km | Executive Engineer, PWD, NH Division, Kollam | IWAI/COCH/12(2)/2013/541 dated 01.09.2015 | 09/01/2015 | 11/10/2015 | 41.85 | 7.6 |
13 | Construction of Lock at Thanneermukkom barrage | Chainage 75.10 Km | Executive Engineer K.D. Sub-Division, Irrigation Department, Govt. of Kerala | IWAI/PLNW3/18/93 | 01/01/2015 | 01/22/2015 | 14 | 7.3 |
14 | Construction of Road Bridge across Mattancherry channel | Chainage 39.75 km | Executive Engineer, PWD Road Division, Ernakulam, Govt. of Kerala | IWAI/PLNW-3/18/93 Vol-II | 12/09/2014 | 02/16/2015 | 47 | > (Greater Than)7 |
15 | Construction of Foot Over Bridge at Chavara Quilon | Ch. 169.40 km | M/s Kerala Electrical & Allied Engineering Ltd. | IWAI/PLNW-3/18/93 | 07/09/2014 | 08/01/2014 | > (Greater Than)40.5 | > (Greater Than)7 |
16 | laying 110kV EHT line across NW -3 at Cherai | chainage 14.4 km | Executive Engineer Kerala Electricity Board | IWAI/PLNW-3/18/93 | 02/21/2014 | 05/27/2014 | 221 | 20.45 |
17 | Construction of Road Bridge at Vaisyambhagam | 6 km from Thakazhy Bridge | Assistant Engineer (PWD) bridges section Thakazhy | No. 101/AE/2010 Dated 17.10.2013 | 10/17/2013 | 07/22/2014 | 47 | 7 |
18 | Construction of Bridge across NW-3 at Pallana on Karuvatta- Kumarakodi Road | Chainage 128.5 Km | Assistant Engineer, Bridges section, Edatua, govt of Kerala | IWAI/PLNW3/18/93 | 07/23/2013 | 05/21/2014 | 47 | 7 |
19 | construction of Road Bridge at Munambam | Chainage 5.5 Km | Executive Engineer, CPWD (Roads), Thrissur | IWAI/PLNW3/18/93 | 02/16/2013 | 06/04/2013 | 45 | 12 |
20 | Construction of Foot Over Bridge at KV Jetty | Ch. 130 Km in near KV Jetty in WCC Canal | District Collector, Alappuzha | IWAI/PLNW3/18/93 | 11/09/2012 | 12/31/2012 | > (Greater Than)73 | > (Greater Than)7.5 |
21 | Permission for providing Girder Support for EOT crane in Udyogmandal Canal | Ch. 22.50 Km in Udyogmandal Canal | Chief Engineer (Tech.Ser.)UG, FACT ltd | IWAI/PLNW3/18/93 | 07/02/2012 | 12/05/2012 | 0 | 0 |
22 | Construction of Road Bridge at Munambam in near Kottapuram | Ch. 5.50 Km near Kottapuram | Executive Engineer, PWD, Trissur | IWAI/PLNW3/18/93 | 02/16/2012 | 06/04/2013 | > (Greater Than)45 | > (Greater Than)12 |
23 | Construction of 220 KV Power Line from Veeyapuram to Punnapra | ThandapraTakazhi, Alappuzha, Ch. 119 Km | Project Manager, Kerala State Elect. Board, Alappuzha. | IWAI/PLNW3/18/93 | 11/10/2010 | 01/05/2011 | > (Greater Than)192 | > (Greater Than)22.61 |
24 | YasoramSkycity Project across NW-3 at Maradu | Maradu | Managing Director, Yasoraminfra Developers Pvt. Ltd. Convent Road, Ernakulam, Kochi | IWAI/PLNW3/18/93 | 10/15/2008 | 10/23/2008 | > (Greater Than)40 | > (Greater Than)7 |
25 | Construction of KallummuoottilKadavu Bridge across TS Canal | Chainage 94 Km | Executive Engineer, Roads Division PWD, Kollam | IWAI/PLNW3/18/93 | 05/07/2008 | 08/29/2008 | > (Greater Than)40 | > (Greater Than)7 |
S. No. | Name of Structure | Location | Applicant Name | Reference | Applicant Date | Noc Issued Date | Approved Clearance in (m) | |
---|---|---|---|---|---|---|---|---|
Horizontal | Vertical | |||||||
1 | Construction of Bridge | Krishnapatnam,Nellore(Dt.),A.P. Buckingham Canal(Under Class-II) | Project Manager,APPDCL Hyderabad,Andhra Pradesh | No. IWAI/PL-13(2)/2001/GEN/NW-4 Vol.II | 10/11/2012 | 02/19/2013 | 40 | 5.5 |
2 | Construction of Pipeline Bridge | Km 14 R&B milestone near sugar factorySamalkot A.P.,Samalkot canal(Under Class-I) | Engineer-in chief(Irrigation),irrigation & CAD department,hyderabad,andhra Pradesh | No. IWAI/PL-13(2)/2001/GEN/NW-4 /Pt-II | 05/06/2012 | 05/17/2012 | 38 | 6 |
3 | Construction of Bridge | Thamminapatnam(vill),Nellore(Dt.) A.P.,Buckingham Canal(Under Class-II) | Sr.Vice President(Commercial),Meenakshi Energy Pvt.Ltd.Hyderabad,Andhra pradesh | No. IWAI/PL-13(2)/2001/GEN/NW-4 Vol.II | 09/19/2011 | 02/23/2013 | 45 | 6.32 |
4 | Construction of Bridge | Km 6.839 0f eluru canal,near Gundala in Krishna(Dt),A.P.,Eluru Canal(Under class-I) | Engineer-in chief(Irrigation),Irrigation&CAD department | No. IWAI/PL-13(2)/2001/GEN/NW-4 | 07/11/2011 | 05/14/2012 | 37.11 | 7.48 |
5 | Construction of Bridge | Krishnapatnam,Nellore(Dt.),A.P. Buckingham Canal(Under Class-II) | Project Director,Coastal Andhra Power Limited,C/o Relaince communivations Ltd. Chinnapadugupadu,Kavali mandal,Nellore Dt. A.P. | No. IWAI/PL-13(2)/2001/GEN/NW-4 | 12/24/2010 | 04/27/2011 | 32 | 5 |
6 | Construction of Bridge | Krishnapatnam,Nellore(Dt.),A.P. Buckingham Canal(Under Class-II) | Chief Operating Officer,Thermal Powertech Corporation India Ltd. Hyderabad,Andhra Pradesh | No. IWAI/PL-13(2)/2001/GEN/NW-4 | 07/26/2010 | 09/14/2010 | 32 | 5 |
7 | Construction of Bridge | Iskapalli,Nellore(Dt.) A.P.,Buckingaham Canal(Under Class-II) | The Executive Engineer,R&B Division,Kavalli,NelloreDt. Andhra Pradaesh | No. IWAI/PL-13(2)/2001/GEN/NW-4 Vol.II | 04/06/2010 | 07/25/2013 | 33.7 | 5.18 |
8 | Construction of Bridge | Krishnapatnam,Nellore(Dt.),A.P. Buckingham Canal(Under Class-II) | Project Director,Coastal Andhra Power Limited,C/o Relaince communivations Ltd. Chinnapadugupadu,Kavali mandal,Nellore Dt. A.P. | No. IWAI/PL-13(2)/2001/GEN/NW-4 | 10/22/2009 | 12/23/2009 | 50 | 5 |
9 | Construction of Bridge for coal conveyor and CW pipe line | Ennore creek Buckingham Canal(Under Class-II) | Jt.General Manager(T),RITES Ltd.Secunderabad,Andhra Pradesh | No.IWAI/PL/13(2)/2001/GEN/NW-4 | 02/05/2009 | 03/03/2010 | 40.9 | 7.17 |
S. No. | Name of Structure | Location | Applicant Name | Reference | Applicant Date | Noc Issued Date | Approved Clearance in (m) | |
---|---|---|---|---|---|---|---|---|
Horizontal | Vertical | |||||||
1 | Construction of Railway Bridge | Near Barachira High School(near Gholpukur),Hijli Tdal Canal(Under Class-II) | Dy.chief Engineer(Con),Construction Organisation-Civil Engg.,South Eastern Railay,Kharagpur | No. IWAI/PL-13(2)/2001/GEN/NW-5 | 07/19/2010 | 09/17/2010 | 45.7 | 5 |
S. No. | Name of Structure | Location | Applicant Name | Reference | Applicant Date | Noc Issued Date | Approved Clearance in (m) | |
---|---|---|---|---|---|---|---|---|
Horizontal | Vertical | |||||||
1 | LAC -ADS-Koothumukkal-Chirakkal-Cherupuzha Thodu project Augmentation sheme in painoor Kayal lift irrigation project in Edathuruthy Panchayat of Kaipamangalam Constituency-Sanction for pipeline crossing through PC Canal | Chainage- 22.5 km in extended stretch of NW-3 (Kottapuram to Kozhikode) | The Executive Engineer office of the executive engineer, Irrigation Division, Thrissur, Kerala | IWAI/NC/Pipeline/PC Canal/2018 | 08/06/2018 | 11/26/2018 | - | - |
2 | Underground cable crossing Canoli Canal to Kerla state Electricity Board Ltd. Thrissur | Chainage - 5.0 km in extended of NHW-3 (Kottapuram to Kozhikode) | The Assistant Executive Engineer Office of the Assistant Executive Engineer Transmission Construction Sub Division, Viyyur, Vydyuthi Bhavanam, Kottappur am, Thrissur | IWAI/NC/Pipeline/Canoli Canal/2018 | 03/10/2018 | 11/26/2018 | - | - |
3 | Construction of Bader Palli Bridge across Canoli Canal in Malapuram District | Tanur in Malappuram Dist. | The Extensive Engineer , PWD Manjeri, Kerla | 08/17/2017 | 11/10/2017 | 40 | 6 | |
4 | Construction of KARMA Bridge at Ponnani Harbour across Canoli Canal | Chainage -86.5 km in extended stretch if NW-3 ) Kottapuram to Kozhikode) | The Extensive Engineer, PWD Road Division, Manjeri, Kerala | IWAI/NC/KARMA/2017 | 08/09/2017 | 10/17/2017 | 45 | 6 |
5 | Construction iof Suspension bridge across Canoli Canal, Malappuram | Chainage- 113.0 km is extended stretch of NW-3 (Kottapuram to Kozhikode) | Executive Engineer, L.S.G.D Division, Malappuram District Panchayath, Civil Station, Malappuram- 676505 | IWAI/PLNW-3/18/93(145) | 04/18/2017 | 03/26/2021 | 45 | 7 |